Enhancing the resilience of Verdant Hills’s mobility while reducing GHG emissions and environmental impacts of transportation and land use.

Sector Action Progress

Reporting Period: 2026
Not Started14In Development1Underway1Completed1Ongoing0On Hold0

Reporting Period: 2026

Data summary: Reporting period 2026: 17 supporting actions reported. Not Started: 14, In Development: 1, Underway: 1, Completed: 1, Ongoing: 0, On Hold: 0.

TL 1: Promote community wide efforts to reduce Vehicle Miles Traveled (VMT) in alignment with county, state, and metropolitan council plan goals.

Supporting Action Progress

Not Started3In Development1Underway0Completed1Ongoing0On Hold0

Reporting Period: 2026

Data summary: Reporting period 2026: 5 supporting actions of 5 reported. Not Started: 3, In Development: 1, Underway: 0, Completed: 1, Ongoing: 0, On Hold: 0.

Progress Metrics

VMT

Million Miles Driven

379.35

Reporting Period: 2026

On Track to Meet Goal
2016202020242028203220360150300600
  • Reported Actuals
  • Original Plan Pathway

The Original Plan Pathway and Required Pathway from Latest Data coincide, so only one line is shown.

Baseline: 380-0.65 (-0.2%)

Data summary: Reporting period 2026: VMT is 379.35 Million Miles Driven. Baseline (2013): 380 Million Miles Driven. Decrease: -0.65 Million Miles Driven (-0.2%). Status: On Track to Meet Goal.

Progress Narrative

What We've Accomplished

Verdant Hills continued implementing the transportation priorities established through the Comprehensive Plan. New and reconstructed transportation projects improved sidewalk continuity, pedestrian crossings, bicycle connections, and accessibility in several priority areas. The City also strengthened coordination between transportation planning, capital improvement programming, and development review so that network connections can be addressed earlier in the planning process.

Where we’ll focus over the next year

The City will continue advancing high-priority network improvements while pursuing regional, state, and federal transportation funding. The City will place particular emphasis on closing short but important gaps, improving connections to transit, and creating safer routes to schools, parks, commercial areas, and community facilities.

Reporting Period: 2026

TL 2: Collaborate with public transit partners to support and promote public transit initiatives in alignment with county, state, and metropolitan council plan goals.

Supporting Action Progress

Not Started3In Development0Underway0Completed0Ongoing0On Hold0

Reporting Period: 2026

Data summary: Reporting period 2026: 3 supporting actions of 3 reported. Not Started: 3, In Development: 0, Underway: 0, Completed: 0, Ongoing: 0, On Hold: 0.

Progress Metrics

Public Transit Utilization

%

1.83

Reporting Period: 2026

On Track to Meet Goal
2016202020242028203220360248
  • Reported Actuals
  • Original Plan Pathway

The Original Plan Pathway and Required Pathway from Latest Data coincide, so only one line is shown.

Baseline: 3.26-1.43 (-43.9%)

Data summary: Reporting period 2026: Public Transit Utilization is 1.83 %. Baseline (2013): 3.26 %. Decrease: -1.43 % (-43.9%). Status: On Track to Meet Goal.

Progress Narrative

What We've Accomplished

Verdant Hills advanced improvements at selected transit stops and strengthened connections between transit, sidewalks, trails, and bicycle routes. The City supported a seasonal shared-mobility demonstration that provided information about potential demand, preferred locations, safety needs, and program accessibility. Several local employers also began promoting transit, bicycling, carpooling, and flexible commuting options using City and regional resources.

Where we’ll focus over the next year

Verdant Hills will evaluate lessons from the shared-mobility demonstration and determine whether a longer-term program is appropriate. The City will also continue improving transit-stop access, expand employer participation, and explore commuter incentives that could be incorporated into municipal employee-benefit programs.

Reporting Period: 2026

TL 3: Encourage increased density requirements as part of Metro Council's comprehensive planning efforts in alignment with county, state, and metropolitan council plan goals.

Supporting Action Progress

Not Started1In Development0Underway1Completed0Ongoing0On Hold0

Reporting Period: 2026

Data summary: Reporting period 2026: 2 supporting actions of 2 reported. Not Started: 1, In Development: 0, Underway: 1, Completed: 0, Ongoing: 0, On Hold: 0.

Progress Metrics

Population Density

People Per Acre of Developed Land

7.18

Reporting Period: 2026

On Track to Meet Goal
2016202020242028203220360248
  • Reported Actuals
  • Original Plan Pathway

The Original Plan Pathway and Required Pathway from Latest Data coincide, so only one line is shown.

Baseline: 7.1+0.08 (+1.1%)

Data summary: Reporting period 2026: Population Density is 7.18 People Per Acre of Developed Land. Baseline (2013): 7.1 People Per Acre of Developed Land. Increase: +0.08 People Per Acre of Developed Land (+1.1%). Status: On Track to Meet Goal.

Progress Narrative

What We've Accomplished

Verdant Hills adopted targeted zoning updates that allow a broader range of housing types and mixed-use development in locations served by transit and existing infrastructure. Updated development-review practices place greater emphasis on pedestrian connections, bicycle access, open-space connections, climate mitigation, and compatibility with surrounding neighborhoods. The City also began tracking how new development supports housing choice and access to daily destinations.

Where we’ll focus over the next year

The City will monitor the effects of the zoning changes and identify adjustments needed to improve implementation. Staff will continue working with developers, residents, and community partners to support equitable development, protect natural resources, and ensure that growth strengthens access to transportation, housing, services, and open space.

Reporting Period: 2026

TL 4: Promote zero and reduced emission vehicle use in the City of Verdant Hills in alignment with county, state, and metropolitan council plan goals.

Supporting Action Progress

Not Started5In Development0Underway0Completed0Ongoing0On Hold0

Reporting Period: 2026

Data summary: Reporting period 2026: 5 supporting actions of 5 reported. Not Started: 5, In Development: 0, Underway: 0, Completed: 0, Ongoing: 0, On Hold: 0.

Progress Metrics

Community-wide Zero Emission Vehicles

Registered EVs

0.75

Reporting Period: 2026

On Track to Meet Goal
2016202020242028203220360200040008000
  • Reported Actuals
  • Original Plan Pathway

The Original Plan Pathway and Required Pathway from Latest Data coincide, so only one line is shown.

Baseline: 0+0.75

Data summary: Reporting period 2026: Community-wide Zero Emission Vehicles is 0.75 Registered EVs. Baseline (2013): 0 Registered EVs. Increase: +0.75 Registered EVs . Status: On Track to Meet Goal.

Progress Narrative

What We've Accomplished

Verdant Hills added its first group of electric vehicles to the municipal fleet and expanded charging capacity at City facilities. Fleet-replacement planning now considers total ownership costs, operational requirements, available incentives, and emissions performance. The City also strengthened lower-emission vehicle expectations in applicable service procurements and continued promoting residential, workplace, and publicly accessible charging.

Where we’ll focus over the next year

Verdant Hills will prepare for additional light- and medium-duty vehicle replacements, pursue funding for charging infrastructure, and evaluate specialized vehicles as suitable models become available. The City will also continue improving public information about electric transportation options and incentives.

Reporting Period: 2026

TL 5: Improve the fuel efficiency of City fleet combustion engine fleet in alignment with county, state, and metropolitan council plan goals.

Supporting Action Progress

Not Started2In Development0Underway0Completed0Ongoing0On Hold0

Reporting Period: 2026

Data summary: Reporting period 2026: 2 supporting actions of 2 reported. Not Started: 2, In Development: 0, Underway: 0, Completed: 0, Ongoing: 0, On Hold: 0.

Progress Metrics

City fleet fuel use

Gallons of fuel

108,937.94

Reporting Period: 2026

On Track to Meet Goal
20162020202420282032203604000080000160000
  • Reported Actuals
  • Original Plan Pathway

The Original Plan Pathway and Required Pathway from Latest Data coincide, so only one line is shown.

Baseline: 94,135+14,802.94 (+15.7%)

Data summary: Reporting period 2026: City fleet fuel use is 108,937.94 Gallons of fuel. Baseline (2013): 94,135 Gallons of fuel. Increase: +14,802.94 Gallons of fuel (+15.7%). Status: On Track to Meet Goal.

Progress Narrative

What We've Accomplished

Verdant Hills incorporated telematics review and eco-driving expectations into routine fleet management. Departments used vehicle data to reduce avoidable idling, improve routing, identify maintenance needs, and make more informed vehicle-replacement decisions. The City also improved coordination between fleet-efficiency efforts and its longer-term zero-emission fleet transition strategy.

Where we’ll focus over the next year

The City will refine fleet-performance indicators and continue targeted training for vehicle classes and departments with the greatest improvement opportunities. Verdant Hills will also evaluate whether additional vehicles can be reassigned, downsized, shared between departments, or replaced with zero-emission alternatives.

Reporting Period: 2026